Schedule

Announced and approvedJul 7, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Lark Harbour
Construction start
Aug 20, 2017(actual)
Construction end
Feb 5, 2020(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 26, 2017
  • Construction end17 months lateforecast Aug 23, 2018