Water and Sewer System, Phase 2
Lark Harbour, Newfoundland and Labrador
Federal contribution
$563,890
Federal share41%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Lark Harbour
- Construction start
- Aug 20, 2017(actual)
- Construction end
- Feb 5, 2020(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 26, 2017
- Construction end17 months lateforecast Aug 23, 2018
Also in Lark Harbour