Water Treatment Plant & Water Reservoir

Long Harbour-Mount Arlington Heights, Newfoundland and Labrador

completeDrinking WaterCC
Federal contribution
$471,698
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010201220142016
Built
Program
Building Canada Fund - Communities Component
Construction start
Jun 1, 2014(actual)
Construction end
Mar 15, 2017(actual)

Against the original forecast

  • Construction start21 months lateforecast Sep 1, 2012
  • Construction end11 months lateforecast Mar 31, 2016