Waterline Replacement Phase 4
Long Harbour-Mount Arlington Heights, Newfoundland and Labrador
Federal contribution
$237,443
Federal share40%
of $593.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 16, 2026
202420252026
Built
Approved 2.7 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Long Harbour-Mount Arlington Heights
- Construction start
- Apr 22, 2024(actual)
- Construction end
- Jul 9, 2024(actual)
Against the original forecast
- Construction start2 weeks earlyforecast May 6, 2024
- Construction end5 months earlyforecast Dec 15, 2024
Also in Long Harbour-Mount Arlington Heights
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67351 in the federal list. How to read these figures.