Waterline Replacement Phase 4

Long Harbour-Mount Arlington Heights, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$237,443
Federal share40%

of $593.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 16, 2026
202420252026
Built

Approved 2.7 years before the announcement.

Program
Green Infrastructure Stream
Construction start
Apr 22, 2024(actual)
Construction end
Jul 9, 2024(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast May 6, 2024
  • Construction end5 months earlyforecast Dec 15, 2024