Waterline Replacement Phase II
Long Harbour-Mount Arlington Heights, Newfoundland and Labrador
Federal contribution
$175,160
Federal share40%
of $437.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202320242025
Built
Approved 2.3 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Long Harbour-Mount Arlington Heights
- Construction start
- Sep 12, 2023(actual)
- Construction end
- Nov 17, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2023
- Construction end6 weeks earlyforecast Dec 31, 2023
Also in Long Harbour-Mount Arlington Heights
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65398 in the federal list. How to read these figures.