Upgrading and Repaving of Route 202 Long Harbour
Long Harbour-Mount Arlington Heights, Newfoundland and Labrador
Federal contribution
$1.6M
$1,569,335
Federal share45%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 11, 2009
ApprovedMay 26, 2009
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Newfoundland and Labrador
- Construction start
- Jun 15, 2009(actual)
- Construction end
- Dec 14, 2009(actual)
Against the original forecast
- Construction start3 months earlyforecast Sep 20, 2009
- Construction end2 weeks lateforecast Nov 30, 2009
Also in Long Harbour-Mount Arlington Heights
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34758 in the federal list. How to read these figures.