Station Road Sanitary Sewer Upgrades
Corner Brook, Newfoundland and Labrador
Federal contribution
$215,882
Federal share32%
of $669.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- City of Corner Brook
- Construction start
- Aug 4, 2009(actual)
- Construction end
- Sep 13, 2010(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Sep 1, 2009
- Construction end7 months lateforecast Jan 30, 2010
Also in Corner Brook
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26675 in the federal list. How to read these figures.