Back to projects

East Valley Road North Storm Sewer-Phases 1,3,4

Corner Brook, Newfoundland and Labrador

completeWastewaterCC Top Up
Federal contribution
$338,973
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Corner Brook
Construction start
Jun 4, 2009(actual)
Construction end
Mar 11, 2011(actual)

Against the original forecast

  • Construction start4 months earlyforecast Oct 1, 2009
  • Construction end11 months lateforecast Mar 28, 2010

Also in Corner Brook

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26681 in the federal list. How to read these figures.