Back to projects

Street Upgrading

Corner Brook, Newfoundland and Labrador

completeHighways and RoadsCC Top Up
Federal contribution
$369,685
Federal share32%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Corner Brook
Construction start
Aug 30, 2009(actual)
Construction end
Dec 3, 2010(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Oct 1, 2009
  • Construction end12 months lateforecast Nov 30, 2009

Also in Corner Brook

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26683 in the federal list. How to read these figures.