Storm Sewer Upgrades
Corner Brook, Newfoundland and Labrador
Federal contribution
$476,044
Federal share29%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010201220142016
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Corner Brook
- Construction start
- Aug 31, 2010(actual)
- Construction end
- Mar 15, 2017(actual)
Against the original forecast
- Construction start11 months lateforecast Oct 1, 2009
- Construction end11 months lateforecast Mar 31, 2016