Road Upgrading

Port Saunders, Newfoundland and Labrador

completeHighways and RoadsCC
Federal contribution
$272,091
Federal share33%

of $816.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Port Saunders
Construction start
Jul 6, 2010(actual)
Construction end
Dec 23, 2010(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 1, 2010
  • Construction end3 months lateforecast Sep 30, 2010

Also in Port Saunders

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26723 in the federal list. How to read these figures.