Replacement of Lift Station #1 and #2
Port Saunders, Newfoundland and Labrador
Federal contribution
$185,261
Federal share40%
of $463.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 16, 2026
2023202420252026
Built
Approved 3.5 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Port Saunders
- Construction start
- Sep 25, 2024(actual)
- Construction end
- Apr 16, 2025(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2024
- Construction end5 months lateforecast Nov 29, 2024
Also in Port Saunders
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65197 in the federal list. How to read these figures.