Replacement of Lift Station #1 and #2

Port Saunders, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$185,261
Federal share40%

of $463.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 16, 2026
2023202420252026
Built

Approved 3.5 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Port Saunders
Construction start
Sep 25, 2024(actual)
Construction end
Apr 16, 2025(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2024
  • Construction end5 months lateforecast Nov 29, 2024