Water Storage Tank Replacement
Port Saunders, Newfoundland and Labrador
Federal contribution
$486,619
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2018
201920202021
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Port Saunders
- Construction start
- Jun 1, 2020(actual)
- Construction end
- Oct 1, 2021(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jun 30, 2020
- Construction end3 months earlyforecast Dec 31, 2021