Coastal Erosion Protection
Port Saunders, Newfoundland and Labrador
Federal contribution
$293,287
Federal share40%
of $733.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 7, 2024
20232024
Built
Approved 2.1 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Port Saunders
- Construction start
- Jun 5, 2023(actual)
- Construction end
- Jul 14, 2023(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 3, 2023
- Construction end4 months earlyforecast Oct 29, 2023