Wastewater Conveyance System to New WWTP

Pictou, Nova Scotia

completeWastewaterCC
Federal contribution
$483,673
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Pictou
Construction start
Apr 30, 2009(actual)
Construction end
Mar 7, 2011(actual)

Against the original forecast

  • Construction start5 months earlyforecast Sep 15, 2009
  • Construction end3 weeks earlyforecast Mar 31, 2011