Delta: Westham Island Dike (Trim Road) Upgrade

Delta, British Columbia

completeDisaster MitigationCC Top Up
Federal contribution
$49,173
Federal share18%

of $266.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Oct 15, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 16, 2010

Also in Delta