Chilliwack - East Dike Upgrades, Greyell Section

Chilliwack, British Columbia

completeDisaster MitigationCC Top Up
Federal contribution
$388,633
Federal share22%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Chilliwack
Construction start
Apr 21, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start7 months lateforecast Sep 24, 2009