Sewer Main Replacement - Long Hill Road
Federal contribution
$61,250
Federal share33%
of $183.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Mahone Bay
- Construction start
- Aug 5, 2009(actual)
- Construction end
- Dec 15, 2009(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 2, 2009
- Construction end6 weeks lateforecast Oct 31, 2009
Also in Mahone Bay