Langley - West Langley Dike Upgrade

Langley, British Columbia

completeDisaster MitigationCC Top Up
Federal contribution
$314,989
Federal share22%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Township of Langley
Construction start
Nov 16, 2010(actual)
Construction end
Apr 15, 2011(actual)

Against the original forecast

  • Construction start12 months lateforecast Nov 15, 2009
  • Construction end7 months earlyforecast Oct 31, 2011

Also in Langley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26971 in the federal list. How to read these figures.