Langley - West Langley Dike Upgrade
Federal contribution
$314,989
Federal share22%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of Langley
- Construction start
- Nov 16, 2010(actual)
- Construction end
- Apr 15, 2011(actual)
Against the original forecast
- Construction start12 months lateforecast Nov 15, 2009
- Construction end7 months earlyforecast Oct 31, 2011
Also in Langley