Back to projects

Water Supply Improvements

Pictou, Nova Scotia

completeDrinking WaterCC Top Up
Federal contribution
$128,349
Federal share33%

of $385.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
201120122013201420152016
Built

Approved 5.3 years before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Pictou
Construction start
Dec 18, 2010(actual)
Construction end
Oct 27, 2011(actual)

Against the original forecast

  • Construction end8 weeks lateforecast Aug 31, 2011

Also in Pictou

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27093 in the federal list. How to read these figures.