East Delta - Boundary Bay Dyke Foreshore Upgrade
Federal contribution
$183,345
Federal share26%
of $700.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- District Municipality of Delta
- Construction start
- Oct 1, 2010(actual)
- Construction end
- Jan 6, 2011(actual)
Against the original forecast
- Construction start10 months lateforecast Nov 26, 2009
- Construction end3 months earlyforecast Mar 31, 2011
Also in Delta