Reconstruction of Brock Street

Gananoque, Ontario

completeHighways and RoadsCC Top Up
Federal contribution
$2.1M
$2,102,999
Federal share45%

of $4.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Separated Town of Gananoque
Construction start
Sep 1, 2009(actual)
Construction end
Oct 30, 2011(actual)