Sewage Lagoon Desludging
Federal contribution
$200,000
Federal share33%
of $600.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 22, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Gananoque
- Construction start
- Dec 4, 2009(actual)
- Construction end
- Oct 1, 2010(actual)
Against the original forecast
- Construction start5 months lateforecast Jul 1, 2009
- Construction end6 months earlyforecast Mar 31, 2011
Also in Gananoque
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30432 in the federal list. How to read these figures.