Force Main and East End Pumping Station upgrade

Gananoque, Ontario

completeWastewaterCWWF
Federal contribution
$336,767
Federal share37%

of $910.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2017
2018201920202021
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Gananoque
Construction start
May 1, 2017(actual)
Construction end
Jun 30, 2021(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Mar 31, 2017
  • Construction end3 months lateforecast Mar 31, 2021