Sanitary Sewer Infiltration Control
Federal contribution
$150,000
Federal share33%
of $450.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Gananoque
- Construction start
- Nov 23, 2009(actual)
- Construction end
- Oct 31, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Sep 1, 2009
- Construction end5 months earlyforecast Mar 31, 2011
Also in Gananoque