Construction of Fort Frances Public Library and Technology Centre
Federal contribution
$955,032
Federal share21%
of $4.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Fort Frances
- Construction start
- Jul 6, 2009(actual)
- Construction end
- May 31, 2010(actual)
Against the original forecast
- Construction end4 weeks lateforecast Apr 30, 2010
Also in Fort Frances
- Rainycrest Long Term Care Home - HVAC Upgrades and Replacement$2.3M
- Revitalization of the Fort Frances Memorial Sports Centre$2.0M
- Rainycrest LTC Sprinkler System$1.6M
- Reconstruction of Colonization Road East from Scott Street intersection to just north of 5th Street Intersection$948.0K
- Reconstruction of Colonization Road West$890.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27638 in the federal list. How to read these figures.