Back to projects

Rainycrest LTC Sprinkler System

Fort Frances, Ontario

underwayHealthcare InfrastructureCVRIS
Federal contribution
$1.6M
$1,558,652
Federal share83%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
2022
BuiltForecast

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 31, 2021(actual)
Construction end
Sep 20, 2022(forecast)

Against the original forecast

  • Construction start4 months lateforecast May 3, 2021

Also in Fort Frances

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59640 in the federal list. How to read these figures.