Reconstruction of Colonization Road East from Scott Street intersection to just north of 5th Street Intersection
Federal contribution
$948,023
Federal share33%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 11, 2015
20162017
Built
Approved 8 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Fort Frances
- Construction start
- May 27, 2016(actual)
- Construction end
- Jun 15, 2017(actual)
Against the original forecast
- Construction end6 weeks earlyforecast Jul 30, 2017
Also in Fort Frances
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46225 in the federal list. How to read these figures.