Revitalization of the Fort Frances Memorial Sports Centre
Federal contribution
$2.0M
$1,999,885
Federal share38%
of $5.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 23, 2021
today
2021202320252027
BuiltForecast
Approved 4 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Fort Frances
- Construction start
- Aug 30, 2021(actual)
- Construction end
- Dec 31, 2026(forecast)
Against the original forecast
- Construction start4 weeks lateforecast Aug 2, 2021
Also in Fort Frances
- Rainycrest Long Term Care Home - HVAC Upgrades and Replacement$2.3M
- Rainycrest LTC Sprinkler System$1.6M
- Construction of Fort Frances Public Library and Technology Centre$955.0K
- Reconstruction of Colonization Road East from Scott Street intersection to just north of 5th Street Intersection$948.0K
- Reconstruction of Colonization Road West$890.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57974 in the federal list. How to read these figures.