Improvements to Sunset Drive
Federal contribution
$40,000
Federal share33%
of $120.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of Schreiber
- Construction start
- Sep 3, 2009(actual)
- Construction end
- Sep 10, 2009(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 17, 2009