Water and Sewer Replacement - Front Street

Wolfville, Nova Scotia

completeWastewaterCC
Federal contribution
$295,900
Federal share33%

of $887.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 6, 2009
20092010
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Wolfville
Construction start
May 31, 2010(actual)
Construction end
Sep 17, 2010(actual)

Against the original forecast

  • Construction start12 months lateforecast Jun 1, 2009
  • Construction end6 months earlyforecast Mar 31, 2011

Also in Wolfville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28162 in the federal list. How to read these figures.