Back to projects

Wolfville Active Transportation Network

Wolfville, Nova Scotia

underwayActive TransportationGIS
Federal contribution
$1.3M
$1,337,364
Federal share40%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2024
today
202320242025202620272028
BuiltForecast

Approved 16 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Wolfville
Construction start
Oct 6, 2025(actual)
Construction end
Mar 31, 2028(forecast)

Against the original forecast

  • Construction start3 months lateforecast Jul 1, 2025

Also in Wolfville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66684 in the federal list. How to read these figures.