Wolfville Active Transportation Network
Federal contribution
$1.3M
$1,337,364
Federal share40%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2024
today
202320242025202620272028
BuiltForecast
Approved 16 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Wolfville
- Construction start
- Oct 6, 2025(actual)
- Construction end
- Mar 31, 2028(forecast)
Against the original forecast
- Construction start3 months lateforecast Jul 1, 2025