Town of Wolfville - Wastewater Treatment Facility Expansion Phase 1
Federal contribution
$1.2M
$1,228,076
Federal share40%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2019
20202021
Built
Approved 7 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Wolfville
- Construction start
- Aug 24, 2020(actual)
- Construction end
- May 19, 2021(actual)
Against the original forecast
- Construction start6 months lateforecast Mar 1, 2020
- Construction end7 weeks lateforecast Apr 2, 2021