Back to projects

Town of Wolfville - Wastewater Treatment Facility Expansion Phase 1

Wolfville, Nova Scotia

completeWastewaterRNIS
Federal contribution
$1.2M
$1,228,076
Federal share40%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2019
20202021
Built

Approved 7 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Wolfville
Construction start
Aug 24, 2020(actual)
Construction end
May 19, 2021(actual)

Against the original forecast

  • Construction start6 months lateforecast Mar 1, 2020
  • Construction end7 weeks lateforecast Apr 2, 2021

Also in Wolfville