Wolfville Wastewater Treatment Facility Upgrades - Phase 2
Federal contribution
$2.4M
$2,400,000
Federal share29%
of $8.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 13, 2023
today
2023202420252026
BuiltForecast
Approved 5 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Wolfville
- Construction start
- May 19, 2025(actual)
- Construction end
- Sep 30, 2026(forecast)
Against the original forecast
- Construction start3 months earlyforecast Aug 11, 2025