Resurfacing Work on Highway 62
Federal contribution
$1.3M
$1,300,077
Federal share45%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 28, 2010
ApprovedJul 23, 2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Jun 1, 2010(actual)
- Construction end
- Oct 20, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 15, 2010
- Construction end5 months earlyforecast Mar 31, 2011
Also in Cardston