Hill Spring Waterlines
Federal contribution
$695,000
Federal share50%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- County of Cardston
- Construction start
- Nov 30, 2018(actual)
- Construction end
- Feb 29, 2020(actual)
Against the original forecast
- Construction start5 months lateforecast Jul 1, 2018
- Construction end4 weeks earlyforecast Mar 31, 2020