Cardston Outfall

Cardston, Alberta

completeWastewaterISF
Federal contribution
$1.5M
$1,545,438
Federal share33%

of $4.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Cardston
Construction start
May 3, 2010(actual)
Construction end
Oct 14, 2011(actual)

Against the original forecast

  • Construction start6 months lateforecast Oct 31, 2009
  • Construction end2 weeks earlyforecast Oct 31, 2011

Also in Cardston

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28800 in the federal list. How to read these figures.