Resurfacing Highway 5 from Cardston to South Spring Coulee
Federal contribution
$2.2M
$2,153,605
Federal share50%
of $4.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- May 26, 2010(actual)
- Construction end
- Oct 30, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2010
- Construction end5 months earlyforecast Mar 31, 2011