Back to projects

Road Resurfacing on Highway 679

Big Lakes, Alberta

completeHighways and RoadsISF
Federal contribution
$980,801
Federal share38%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Jun 1, 2010(actual)
Construction end
Jun 4, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2010
  • Construction end4 months earlyforecast Oct 15, 2011

Also in Big Lakes

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28520 in the federal list. How to read these figures.