Kinuso Water Distriubtion Pumphouse and Reservoir
Federal contribution
$2.1M
$2,060,736
Federal share50%
of $4.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
20182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- County of Big Lakes
- Construction start
- Jul 10, 2017(actual)
- Construction end
- Mar 28, 2019(actual)
Against the original forecast
- Construction start4 months lateforecast Mar 6, 2017
- Construction end5 weeks earlyforecast Apr 30, 2019
Also in Big Lakes
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49900 in the federal list. How to read these figures.