Jousard water reservoir
Federal contribution
$1.2M
$1,249,331
Federal share33%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- County of Big Lakes
- Construction start
- Jul 16, 2018(actual)
- Construction end
- Jan 29, 2020(actual)
Against the original forecast
- Construction start2 months lateforecast May 15, 2018
- Construction end4 months lateforecast Sep 30, 2019