Modernising Watercourse Crossing Structures on Highway 33

Big Lakes, Alberta

underwayCapacity BuildingGIS
Federal contribution
$3.9M
$3,852,492
Federal share39%

of $9.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 12, 2024
202420252026
BuiltForecast

Approved 17 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Government of Alberta
Construction start
May 27, 2024(actual)
Construction end
Jul 31, 2026(forecast)

Also in Big Lakes

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67878 in the federal list. How to read these figures.