Replacement of the Span Bridge in the Western Irrigation District (Langdon)
Federal contribution
$398,959
Federal share39%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipal District of Rocky View No. 31
- Construction start
- Jan 11, 2010(actual)
- Construction end
- Jun 4, 2010(actual)
Against the original forecast
- Construction start8 weeks lateforecast Nov 16, 2009
- Construction end8 weeks earlyforecast Jul 31, 2010
Also in Rocky View County