Back to projects

Resurfacing Highway 11 from Horburg to East of Horburg

Clearwater County, Alberta

completeHighways and RoadsISF
Federal contribution
$2.0M
$2,043,259
Federal share49%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Jun 20, 2010(actual)
Construction end
Oct 20, 2010(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2010
  • Construction end5 months earlyforecast Mar 31, 2011

Also in Clearwater County

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28725 in the federal list. How to read these figures.