Rehabilitation of Highway 587
Federal contribution
$662,170
Federal share46%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 29, 2010
2011
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Oct 1, 2010(actual)
- Construction end
- Jul 25, 2011(actual)
Against the original forecast
- Construction end3 months earlyforecast Oct 15, 2011
Also in Clearwater County
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40468 in the federal list. How to read these figures.