Highway 22 - Lane Construction

Clearwater County, Alberta

completeHighways and RoadsISF
Federal contribution
$1.5M
$1,549,873
Federal share50%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJan 28, 2010
ApprovedJul 23, 2010
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Jun 1, 2010(actual)
Construction end
Sep 29, 2010(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jun 15, 2010
  • Construction end6 months earlyforecast Mar 31, 2011