Sunchild Road Resurfacing - Phase 2
Federal contribution
$4.3M
$4,295,226
Federal share32%
of $13.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Clearwater
- Construction start
- Aug 19, 2010(actual)
- Construction end
- Jul 4, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 15, 2010
- Construction end4 weeks earlyforecast Jul 31, 2011
Also in Clearwater County
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28982 in the federal list. How to read these figures.