Sunchild Road Resurfacing - Phase 2

Clearwater County, Alberta

completeHighways and RoadsISF
Federal contribution
$4.3M
$4,295,226
Federal share32%

of $13.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Clearwater
Construction start
Aug 19, 2010(actual)
Construction end
Jul 4, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 15, 2010
  • Construction end4 weeks earlyforecast Jul 31, 2011