Grading - Pipestone Creek Road
Federal contribution
$284,900
Federal share20%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Grande Prairie
- Construction start
- Jul 28, 2009(actual)
- Construction end
- Oct 8, 2009(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Aug 21, 2009
- Construction end12 months earlyforecast Sep 30, 2010
Also in Grande Prairie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28743 in the federal list. How to read these figures.