Range Road 60 Resurfacing
Forty Mile No. 8 (County), Alberta
Federal contribution
$599,305
Federal share32%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Forty Mile
- Construction start
- May 21, 2010(actual)
- Construction end
- Jul 9, 2010(actual)
Against the original forecast
- Construction end3 months earlyforecast Sep 30, 2010