Back to projects

Distribution Pumping Upgrades

Forty Mile No. 8 (County), Alberta

completeDrinking WaterCWWF
Federal contribution
$109,778
Federal share29%

of $377.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
2018201920202021
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
County of Forty Mile No. 8
Construction start
Jul 19, 2017(actual)
Construction end
Dec 31, 2020(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2017
  • Construction end4 weeks earlyforecast Jan 31, 2021