Storage Reservoir Upgrades
Forty Mile No. 8 (County), Alberta
Federal contribution
$617,000
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
20182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- County of Forty Mile No. 8
- Construction start
- Jul 1, 2018(actual)
- Construction end
- May 1, 2019(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 15, 2018
- Construction end8 months earlyforecast Dec 31, 2019